• New pedestrian link bridge at LLA


New pedestrian link bridge at LLA

Date_ 18 April 2016

 

Work continues at LLA with the first section of the pedestrian link bridge being lifted into place on our London Luton Landside Civils Project. The 35 tonne 30m span bridge is being lifted into place with a 350 tonne crane and links the new Core 3 and Core 2 Buildings. The 80m span pedestrian bridge linking the Core 2 to Core 1 Buildings will be delivered to site next month and lifted into place in 3 sections. On completion the pedestrian link bridge and cores will provide a safe pedestrian route from the short term and multi storey car parks to the new terminal entrance.