• New Asphalt Plant
  • New Asphalt Plant


New Asphalt Plant

Date_ 28 August 2015

 New Asphalt Plant, Coleraine

After 6 months of hard work the New Asphalt Plant is now fully functional. The relocation from Five Mile Town to Coleraine started in January 2015 and was completed in June 2015. More than 60 lorry loads were required, which involved a large number of oversized loads. The facility will have 8 cold feed bins, rat recycled asphalt, fibre facilities, 300 tonnes of hot storage plus 4 x bitumen tanks. In addition, a brand new triple burner will facilitate natural gas, premium fuel oil (PFO), and gas oil. Facilities moved included; a laboratory, dust shed and sand shed. The New Asphalt plant in Coleraine is a more efficient plant with higher production capabilities. It has connection to natural gas and is now well located within a company owned quarry facility.