• Parliament Buildings Stormont
  • Parliament Buildings Stormont

 

Whitemountain completed a major resurfacing and maintenance project at Parliament Buildings Stormont.

The work was completed over 4 weekends in March and April in preparation for staging the start of the world famous Giro D’ Italia 2014.

More than 2000 tonnes were scarified from the existing carriageway, 20,000 square metres of asphalt were laid including 10,000m of new lining to Prince of Wales Avenue, Massey Avenue and all the approaches leading to Stormont.