Work has begun on a major street lighting programme between Belfast and Bangor.

The Whitemountain Street Lighting Team are undertaking two major street lighting installation projects as part of our MTC’s at the Springhill Flyover Bangor and the A2 Dual Carriageway.

34 × 12m post top passive safe columns with LED lanterns will be installed at the Springhill Junction Bangor and 265 × 12m hockey stick passive safe columns with LED lanterns will be installed on the A2 Dual Carriageway from Belfast to Bangor starting at Springhill junction towards Belfast.

This is part of a large project to be completed by the end of October.
Work has been scheduled to ensure minimal delay to rush hour traffic, both jobs will be completed under strict traffic management, restricted speeds down to 40mph and restricted working hrs i.e. 9.30 am – 4.30pm and then Tuesdays to Thursday in the evenings 6.30pm – 11.30pm.